Feature: Chinese workers overcome harsh conditions for China-Laos connectivity project

Source: Xinhua| 2019-08-05 20:06:58|Editor: Xiaoxia
Video PlayerClose
LAOS-OUDOMXAY-CHINA-LAOS RAILWAY-TUNNEL-CONSTRUCTION?

Workers of China Railway No. 5 Engineering Group (CREC-5) use ice blocks to cool off at the China-Laos railway Ban Konlouang Tunnel construction site in the Namor District of Oudomxay Province, Laos, Aug. 1, 2019. Rainy season in the Namor District of Oudomxay Province, some 400 km north of the Lao capital Vientiane, is relatively cool in late July, while at the Ban Konlouang Tunnel construction site, located inside mountains there, Chinese workers are sweating. The 9,020-meter Ban Konlouang Tunnel is the second longest tunnel along the China-Laos railway in northern Laos, which is constructed by China Railway No. 5 Engineering Group. (CREC-5/Handout via Xinhua)

by Zhang Jianhua, Wang Shan

VIENTIANE, Aug. 5 (Xinhua) -- Rainy season in the Namor District of Oudomxay Province, some 400 km north of the Lao capital Vientiane, is relatively cool in late July, while at the Ban Konlouang Tunnel construction site, located inside mountains there, Chinese workers are sweating.

The 9,020-meter Ban Konlouang Tunnel is the second longest tunnel along the China-Laos railway in northern Laos, which is constructed by China Railway No. 5 Engineering Group (CREC-5).

With harsh geological conditions of faults, underground rivers, water inrush and mud, the tunnel construction site is known as the "Geological Museum".

The construction has been listed as a key bottleneck of the railway project.

At the construction site, heat waves erupt from the depth of the tunnel, hitting incomers of the tunnel. In the steamer-like tunnel, even standing still, people can feel sweat dropping down.

When the reporter went into the under-construction tunnel in late July, Wang Hong and his Chinese colleagues were kneeling on an ice pile made up of dozens of large ice blocks.

"The happiest thing in this stuffy tunnel is to take a 10-minute rest on the ice pile," Wang Hong said, smearing the sweat off his face. "Without the ice, I really don't know how to continue with the job."

According to Wang Hong, the average temperature in the tunnel exceeds 45 degrees centigrade.

In order to keep cool inside the tunnel and create a better construction environment for the workers, the CREC-5 project management has purchased an ice machine, only for providing some five tons of ice every six hours to cool down the construction sites.

"Look, so much water can be squeezed from my clothes," the man, in his 40s, said with a light smile, adding that working in the tunnel for 10 minutes will turn the clothes into a "raincoat", and working at this environment is prone to serious rheumatism.

Wang Hong, who has been participating in tunnel construction since 1999, has worked in more than 20 tunnels. He said the Ban Konlouang Tunnel of China-Laos railway is the hottest tunnel he has ever worked on and also the tunnel with the most difficulties.

Even so, Wang Hong and his team workers have set a record along the China-Laos railway for the monthly excavation length--186 meters.

After a 10-minute rest, Wang Hong and the workers drank their full kettles of water and then left the ice heap for the tunnel, while another group of Chinese tunnel workers have came.

In the evening, back to the dormitory with Wang Hong and his fellow workers, the reporter found the first thing they did in the dormitory was turning on electric blankets. Although it is relatively cool during rainy season in the year, the temperature at night in Oudomxay can also be around 25 degrees centigrade.

It can not said to be cold, but why do the Chinese tunnel workers turn on the electric blanket?

It turns out that in the rainy season, continuous precipitation not only brings coolness but also dampness. Workers need to prepare electric blankets and spend an hour or so every day to dry up their sheets and quilts.

According to Wang Hong's team worker, Qiu Liping, they are working in the daytime in the tunnel, so they have to prepare electric blankets, instead of dry up the sheets and quilts in the sun.

Qiu Liping said that when waking up in the morning, he can see small drops of water on the quilt because of the recent heavy rains.

"Although the conditions are difficult, joining the Belt and Road construction makes me feel proud. Not only have I enriched my knowledge, but also improved my professional skills," said Qiu.

Being the first overseas route connecting with the railway system in China using Chinese technology and equipment, China-Laos railway is a major project in infrastructure inter-connectivity between China and neighboring countries, and a major project in implementing the Belt and Road Initiative.

Ground-breaking ceremony of the railway was held in December 2015, and the construction of the whole route officially started a year later, while the railway is expected to open to traffic in December 2021.

The China-Laos railway has a length of over 414 km with bridges of 62 km, tunnels of 198 km under construction, linking Mohan-Boten border gate in northern Laos and capital Vientiane. Operating speed on the route is designed at 160 km per hour.

   1 2 3 4 5 Next  

KEY WORDS:
EXPLORE XINHUANET
010020070750000000000000011100001382856631
国产在线观看免费观看| 精品国产你懂的在线观看| 精品午夜一区二区三区久久| 狠狠躁天天躁夜夜躁婷婷| 2020精品国产福利在线观看香蕉| 伊人久久大香线蕉av色婷婷色| 樱桃熟了a级毛片| 国产激情无码一区二区APP| 国产成人精品人人2020视频| 老司机午夜精品网站在线观看| 亚洲综合色吧| 亚洲色婷婷一区二区| gogogo高清免费观看| 亚洲欧洲日韩国内高清| 久久久国产精品黄色片| 亚洲人成色99999在线观看| 国产精品视频免费一区二区三区| 久爱无码精品免费视频在线观看 | 亚洲成av人片在线观看| 免费一区二区无码东京热 | AV老司机AV天堂| 女人张开腿让男人桶爽| 亚洲欧洲国产综合一区二区| 国产亚洲日韩在线一区二区三区| 国模欢欢高清炮交视频| 亚洲日韩精品一区二区三区无码| 国产男女猛烈无遮挡免费视频| 成人看的污污超级黄网站免费| 大地资源二在线视频观看| 午夜一区二区亚洲福利vr| 国产成人精品亚洲日本语言| 香蕉久久人人爽人人爽人人片av| 日日天日日夜日日摸| 久久久久亚洲精品天堂| 91水蜜桃网站在线观看| 99999久久久久久亚洲| 国产九九九九九九九a片| 女人夜夜春高潮爽a∨片| 国产成人综合亚洲欧美日韩| 久久精品国产亚洲av麻豆小说| 成A人片亚洲日本久久|